Status: Please note you should read all Brexit changes to the FCA Handbook and BTS alongside the main FCA transitional directions. Where these directions apply the 'standstill', firms have the choice between complying with the pre-IP completion day rules, or the post-IP completion day rules. To see a full list of Handbook modules affected, please see Annex B to the main FCA transitional directions.

LR 17.2 Requirements for listing and listing applications

Requirements for listing

LR 17.2.1GRP

An issuer to whom this chapter applies will need to comply with LR 2 (Requirements for listing - all securities).

Listing Applications

LR 17.2.2GRP

An issuer to whom this chapter applies will need to comply with LR 3 (Listing applications).